SUBSTATION
|
PROJECT NAME
|
DURATION
|
CLIENT
|
STATUS
|
Spitskop 1 Substation
|
Civil works
|
24 Weeks
|
Eskom
|
Completed 2014
|
Marang Substation
|
Oil dam
|
12 Weeks
|
Eskom
|
Completed 2014
|
Pelly Substation
|
Civil Works
|
32 Weeks
|
Eskom
|
Completed 2014
|
Apollo Spare Transformer Plinths
|
Civil works
|
24 Weeks
|
Eskom Transmission
|
Completed 2012
|
Mine hostels
|
Renovations and Building
|
72 Weeks
|
Harmony Mine
|
Completed 2014
|
Northrand New CNC
|
Building
|
36 Weeks
|
Eskom Distribution
|
Completed 2013
|
Croydon Salvage store
|
Civil and building works
|
16 Weeks
|
Eskom Transmission
|
Completed 2012
|
Dinaledi
|
Transformer Plinth
|
6 Weeks
|
Eskom Transmission
|
Completed 2014
|
Spitskop Transformer Plinth Extension
|
Civil works
|
12 Weeks
|
Daewoo
|
Completed 2014
|
Rehabilitation and upgrading of Azaadville sport complex
|
Civils and Building Works
|
24 Weeks
|
Mogale City Local Municipality
|
Completed 2014
|
Carmel Transformer Plinth Repair
|
Civil works
|
6 Weeks
|
Eskom Transmission
|
Completed 2014
|
X-trata Lion Phase 2
|
Civil works
|
40 Weeks
|
Eskom Transmission
|
Completed 2013
|
NWG Yardstones
|
Supply, spread of yardstones
|
12 Weeks
|
Eskom Transmission
|
Completed 2014
|
Midas Emergency Transformer
|
Civil works
|
36 Weeks
|
Eskom Transmission
|
Completed 2013
|
Merensky
|
Supply and spread yardstones
|
20 Weeks
|
Eskom Transmission
|
Completed 2014
|
Merapi Transformer plinth modification
|
Civil works
|
4 Weeks
|
Eskom Transmission
|
Completed 2013
|
Modification of Transformer plinth at Eiger Substation
|
Civil works
|
6 Weeks
|
Eskom
|
Completed 2014
|
Etna Transformer Plinth modification
|
Civil works
|
3 Weeks
|
Eskom Transmission
|
Completed 2012
|
Spencer Transformer Plinth Repair
|
Civil works
|
24 Weeks
|
Eskom Transmission
|
Completed 2012
|
Tabor Botlokwa 132kv feeder Bay
|
Civil works
|
36 Weeks
|
Eskom Transmission
|
Completed 2011
|
Droerivier Substation Transformer Plinth Modification
|
Civil works
|
24 Weeks
|
Eskom Transmission
|
Completed 2014
|
Acacia Substation 2 x 132kv Feeder
|
Civil works
|
24 Weeks
|
Eskom Transmission
|
Completed 2012
|